Category Archives: Milstein-Rand-Sibley Hall

problems with the third-floor exterior wall of East Sibley Hall

[updated below Oct. 13, 2011 and March 9, 2012] Appendix K of the 2002 New York State Building Code made significant changes to the model 2000 International Building Code (IBC) upon which the New York State Code was based. It allowed a building addition to “increase the area of an existing buiding beyond that permitted under the applicable provisions of Chapter 5 of the Building Code for new buildings” as long as a fire barrier was provided.

Normally, a fire wall — not a fire barrier — would be required in such cases, but NYS legislators wanted to make it easier and less expensive (and therefore less safe) to build additions to existing structures. Whereas it is absolutely clear what a fire wall is, and where it must be placed in relation to the parts of a building it is separating, this hastily contrived NYS appendix doesn’t bother to specify exactly where its alternative fire barrier must be provided.

This wouldn’t be much of a problem if the addition were the same height as the existing building. However, Milstein Hall at Cornell University (OMA – Rem Koolhaas architects) is a two-story building addition connected to Sibley Hall, which is a three-story building (see building section below, adapted from Cornell’s Milstein Hall web site). The architects for Milstein initially had called for a fire barrier between the two buildings, but only on the second-floor where they literally connect. It was only later, when this assumption was challenged, that they added fire barrier protection at all levels where the two buildings come into contact (i.e., at the basement and first-floor levels as well) — see update below. Left with no protection at all is the thrid-floor exterior wall of E. Sibley Hall overlooking Milstein’s green roof.

Section showing Sibley and Milstein Halls (adapted from Cornell's Milstein Hall web site)

Sibley and Milstein Halls (adapted from Cornell's Milstein Hall web site)

This is a problem for two reasons. First, the window openings on the third floor of Sibley have no fire protection. Second, the wooden load-bearing exterior wall of Sibley’s third floor has no fire-resistance rating. None of this was a problem when Sibley was a non-conforming, grandfathered, free-standing building. It becomes a problem with the construction of Milstein Hall.

The 2002 New York State Code (specifically, Section 704.10), under which Milstein was permitted, requires that “opening protectives” be provided “in every opening that is less than 15 feet (4572 mm) vertically above the roof of an adjoining building or adjacent structure that is within a horizontal fire separation distance of 15 feet (4572 mm) of the wall in which the opening is located.” All of the window openings in the third floor of E. Sibley Hall that overlook Milstein Hall qualify under this section for opening protectives. The only exception to this requirement is where the roof construction below the openings has a 1-hour fire-resistance rating and its structure (i.e., the steel beams and girders supporting the roof) has a 1-hour fire-resistance rating. Milstein’s roof structure has no fire-resistance rating, so the exception does not apply.

Not only do Sibley’s third-floor windows require opening protectives, but the entire exterior wall on the third floor of Sibley (facing Milstein Hall) needs to be reconstructed with a 1-hour fire-resistance rating. Footnote “f” in Table 601 (exterior bearing walls) requires that the fire-resistance rating of the wall be not less than that based on fire separation distance (Table 602). Table 602 requires a 1-hour fire-resistance rating for Occupancy Groups A or B if the fire separation distance is less than 5 feet.

The fire separation distance between Sibley and Milstein Halls is 0 feet (they are physically connected), based on the most generous assumption that one can make, i.e., that they are effectively two separate buildings. Actually, Appendix K only allows them to be considered as separate buildings from the standpoint of “area” (K902.2). However, if they were considered as a single building — as would be required under the current building code (i.e., without a fire wall) — then all of this discussion would be moot since Milstein Hall would be clearly noncompliant. Either way one looks at it — as a single building or as two separated buildings — the current situation appears to be noncompliant.

[Update: Oct. 13, 2011] As it turns out, the nonconforming fire barrier placed between Sibley and Milstein Hall — to satisfy the ambiguous requirements of Appendix K from the 2002 Building Code of NYS — is not only nonconforming but also noncompliant. The width of fire-rated openings in such a fire barrier cannot exceed 25 percent of the length of the fire barrier wall. In the image below, the aggregate width of openings is shown graphically in relation to the total length of the fire barrier wall. It can be seen that the opening width greatly exceeds the 25 percent limit:

sibley-2nd-floor-small

[Update: March 9, 2012] A noncompliant solution to the fire barrier problem was proposed and recently installed. At great expense. And completely useless. See my analysis here.

cornell’s fine arts library in Rand Hall

There are plans to move Cornell’s Fine Arts Library from Sibley Hall, where it has existed as a nonconforming (”grandfathered”) occupancy for quite a few years, to Rand Hall, which is now connected to Sibley Hall through newly-constructed Milstein Hall. Because the addition of Milstein Hall was, and is, nonconforming with respect to the current New York State Building Code, it may not be possible to put a library occupancy in Rand Hall. I made a similar argument about placing so-called Group A occupancies in Sibley Hall. This same explanation applies to Group A occupancies in Rand.

A future change to an A-3 (library or lecture hall) occupancy in Rand Hall should not be permitted, because such a change would be replacing an existing occupancy with one of a higher hazard. The relevant code language is as follows: Section 812.4.2.1 of the Existing Building Code of New York State says: “When a change of occupancy group is made to a higher hazard category as shown in Table 812.4.2, heights and areas of buildings and structures shall comply with the requirements of Chapter 5 of the Building Code of New York State for the new occupancy group.” Table 812.4.2 classifies group A-3 spaces as having a “relative hazard” of 2 (with 1 being the highest hazard), and group B spaces (the current occupation of Rand’s 2nd and 3rd floor, per email from City of Ithaca Senior Code Inspector John Shipe) as having a relative hazard of 4 (lowest hazard). Therefore, it is clear that a change from group B to group A-3 constitutes an alteration to a higher hazard occupancy.

With such a change, the building — which under the current building code is defined as Rand-Sibley-Milstein — must conform to the requirements of Chapter 5 of the current Building Code of New York State. What are those requirements? Chapter 5 regulates the allowable heights and areas of buildings, based on construction type and occupancy. Since the fire barrier separating Milstein and Sibley Halls is nonconforming with respect to the current code, it [i.e., the fire barrier — clarification added 10/2/11] cannot be invoked to consider Rand-Milstein Hall as a separate building, as would be the case with a fire wall. Therefore, Rand-Sibley-Milstein must be treated as a single building under the current code, and the height/area limits are as follows: the maximum height is 60 feet; the maximum number of stories is two; and the maximum area on a single floor is at most 22,500 sq.ft. The combined second-floor area for Rand-Sibley-Milstein greatly exceeds this limit of 22,500 sq.ft., and the number of stories in Rand-Sibley-Milstein similarly exceeds the Code limit of two. Based on either of these criteria (floor area or number of stories), any alteration to a higher hazard occupancy should not be permitted, as the requirements of Chapter 5 would not be met, and cannot be met.

In other words, putting the library on the 3rd floor of Rand would violate the Code limit of two stories; putting the library on the 2nd floor of Rand would violate the floor area limit.

[Update: Oct. 13, 2011] The move of the Fine Arts Library into Rand Hall has taken place this past week, in spite of the objections I have raised. Here are a few additional points, for the record:

1. On Oct. 7, 2011, I sent an email to the Milstein Hall project director which included this clarification:

“I didn’t mention this to GW at today’s meeting, but my notes that I gave him on Code issues (attached) state that: ‘the exception [to Section 912.5.1 of the Existing Building Code of NYS] only permits a fire barrier, if used in lieu of a fire wall, to meet area limitations for the new occupancy — NOT height limitations. Only a fire wall can meet both height and area limitations for the new occupancy.’ In other words, the library move to the 3rd floor of Rand will not be in compliance even if the fire barrier between Rand and Milstein is upgraded. Only a fire wall would make such a move compliant. On the other hand, an upgraded fire barrier would appear to allow such a move to the second floor of Rand Hall. In either case, the current fire barrier is noncompliant.”

2. The contention that a library (A-3 occupancy) constitutes a higher hazard occupancy compared to the current use in the Rand Hall space is the underlying reason why such a move is noncompliant. The Code is unambiguous about the occupancy of libraries as A-3. Design studios are not specifically mentioned in the Code; rather, they fall under the Group B definition for educational occupancies above the 12th grade. If there was any doubt about the legitimacy of this classification, the Ithaca Building Department files for Rand Hall contain numerous documents, all confirming that the Group B designation was actually used for the studio spaces in Rand Hall. Older documents in the file show a C5.5 designation; this was the old New York State Code subcategory for Educational occupancies within the “Commercial” category — exactly equivalent to the modern Group B designation. See this document copied from the Rand Hall Building Department file.

3. Even if a fire wall were built between Rand and Milstein Halls, it would still be necessary to upgrade the two egress stairs in Rand Hall, which are noncompliant once the occupancy on the third floor changes to a higher hazard. For details, see my email to the Milstein Hall project director.

milstein – uris comparison

Walking across Cornell’s campus the other day, I was struck by the similarity between Uris Hall, designed by Gordon Bunshaft (Skidmore, Owings & Merrill) in the 1970s, and Paul Milstein Hall, designed by Rem Koolhaas (Office for Metropolitan Architecture – OMA) in the 2000s.

Facade of Uris Hall (S.O.M.) applied to the rendering of Milstein Hall (O.M.A.).

Both buildings consist of  large, essentially square, floor plates supported by rigid frames (vierendeel trusses) lifted off the ground and cantilevered in dramatic fashion from their points of support. Both buildings also hover over large, below-grade, auditoriums: in the case of Uris Hall, the auditorium sits politely under the podium; in Milstein Hall, the auditorium rides a reinforced concrete dome that seems to burst through the ground plane. Both buildings mediate their cantilevered steel superstructures and highly-articulated bases with a glass wrapper designed to enclose space and provide an entry at grade without compromising the visual articulation of superstructure and base.

Official rendering of Milstein Hall.

Code compliance issues in E. Sibley Hall, Cornell

Following is a transcription of an email that I wrote to the Dean of the College of Art, Architecture, & Planning at Cornell University on Sept. 6, 2010 (copied to the Assistant Dean for Administration, AA&P; the Project Director for Milstein Hall; and the Building Commissioner and Deputy Building Commissioner of the City of Ithaca) [9/10/10 updates below]:

Portions of East Sibley and Rand Halls are in serious danger of being noncompliant with the NYS Building Code, and their ability to remain occupied for library, studio/classroom, and office use may be in jeopardy.

Once the floor/roof structure of Milstein Hall is in place, two things immediately occur that threaten the continued occupation of the adjacent, connected buildings.

First, all covered space under the structure of Milstein Hall counts as building area for Sibley Hall whether or not those spaces are enclosed, since a fire barrier is not yet in place to separate the two structures. Under these current circumstances, East Sibley Hall contains floors whose areas — that is, the combined, unseparated, floor areas of East Sibley and Milstein Halls — exceed that allowed by the Code, given the limits imposed by the governing V-B construction type for Sibley Hall.

Second, once the floor/roof structure of Milstein Hall is in place, the windows in Sibley Hall under these covered spaces no longer function as openable windows for the purpose of natural ventilation. I understand that Cornell and City of Ithaca Code Enforcement officials have challenged this contention, but I must insist that it remains true. As I pointed out previously, the Code limits natural ventilation to windows opening to “yards” or “courts.” Yards and courts must be “uncovered space, unobstructed to the sky” (see chapter 2 definitions in the Code). The Code does not permit windows used for natural ventilation to open into any other type of spatial geometry, whether or not “outdoor air” can somehow work its way to the window opening. The Commentary to the Code (written for the International Building Code, or IBC, from which the NYS Code derives) is absolutely unambiguous: “In order that adequate air movement will be provided through openings to naturally ventilated rooms, the openings must directly connect to yards or courts with the minimum dimensions specified in Section 1206” (Commentary for Section 1203.4.3 Openings on yards or courts). Since the openings “must directly connect to yards or courts” and since yards and courts must be “uncovered space, unobstructed to the sky,” the East Sibley windows at or below the second-floor of Milstein do not provide natural ventilation. Without mechanical ventilation that meets the criteria specified in the New York State Mechanical Code, the rooms are noncompliant and should not be occupied. In prior emails, I have outlined why the ad hoc provision of room air conditioner units or fans does not satisfy the requirements of the Mechanical Code. Yet aside from such rooms, it is clear that classrooms (e.g., 142-144 ES) or library spaces (e.g., the entire second-floor F.A.L. In E. Sibley) that have absolutely no mechanical ventilation will certainly not meet those Code requirements.

The second floor of Rand Hall, due to changes in the window configuration that have reduced the openable area, also has problems meeting Code criteria for natural ventilation. The current second-floor studio area (field measurements taken 9/3/10, excluding enclosed computer rooms, etc.) encompasses 5,259 square feet. The required vent area from openable windows is 4% of 5,259, or 210.4 square feet. However, the actual available vent area from openable windows, equal to 15 windows times 11.625 square feet of vent area per window, is only 174.4 square feet total. This is clearly noncompliant, and yet no mechanical ventilation is being planned for the studio space [see prior comments].

It is not my intention to speculate as to why East Sibley Hall and the second floor of Rand Hall are being occupied in spite of these apparent Code violations (lack of required ventilation in Rand and East Sibley Halls; and lack of fire barrier protection in East Sibley Hall). But whatever the reasons, the problems need to be addressed. It seems to me that either the noncompliant spaces should be vacated until Sibley/Milstein/Rand Hall is completed, or the twin problems of ventilation and fire protection should be corrected immediately.

Update 1 (9/10/10):

Two passages from NFPA 241: Standard for Safeguarding Construction, Alteration, and Demolition Operations (1996 version quoted here) support my argument about the immediate need for a fire barrier (the NFPA standard mentions “fire wall,” but the same logic applies to a “fire barrier” used as a substitute for a fire wall) between Sibley Hall and Milstein Hall:

1-1.1
Fires during construction, alteration, or demolition operations are an ever-present threat. The fire potential is inherently greater during these operations than in the completed structure due to previous occupancy hazard and the presence of large quantities of combustible materials and debris, together with such ignition sources as temporary heating devices, cutting/welding/plumber’s torch operations, open fires, and smoking. The threat of arson is also greater during construction and demolition operations due to the availability of combustible materials on-site and the open access.

6-6 Fire Cutoffs.
Fire walls and exit stairways, where required for the completed building, shall be given construction priority for installation… [and yes, the fire barrier is required for the completed building].

Update 2 (9/10/10):

I want to clarify that both of the actions I am recommending (mechanical ventilation for E. Sibley Hall rooms adjacent to Milstein Hall; and installation of a fire barrier in all E. Sibley Hall windows adjacent to Milstein Hall) are already part of the Milstein Hall scope of work. The issue is not whether they are required — they are both required and included in the Milstein Hall budget — but whether E. Sibley Hall can remain occupied during construction without these two items being put into place. In my view, the Code is clear on both issues: E. Sibley Hall should not remain occupied without adequate provision for ventilation and fire protection.

Furthermore, since both of these items are already part of the Milstein Hall scope of work, it is absolutely incomprehensible why the project’s phasing plan did not prioritize these two items so that E. Sibley Hall could remain safely occupied during construction. Well, actually, it is not so incomprehensible: the initial plans and specifications submitted to the City of Ithaca Building Department for a building permit included neither a proper fire barrier nor adequate mechanical ventilation for Sibley Hall. It was only after I raised objections through the FEIS comment process that the architects for Milstein Hall extended their fire barrier to the first and basement floors of Sibley Hall, and accepted the need for mechanical ventilation in Sibley Hall (after deciding to put fixed fire-rated glazing in all E. Sibley windows adjacent to Milstein). These architects still have not admitted that natural ventilation from windows under Milstein Hall is no longer a possibility given Code requirements for “yards” and “courts” adjacent to all windows used for natural ventilation; and continue to maintain that it is only because of the fixed glazing required for their fire barrier design that mechanical ventilation becomes necessary.

Construction of Milstein Hall

I’ve just posted the first of a series of informal “construction” videos showing how Paul Milstein Hall (OMA/Rem Koolhaas) at Cornell University is being built. The homepage for the anticipated video series is here. Ultimately, I hope to add additional short videos dealing in turn with substructure, superstructure, and enclosure systems.

The first video, “Getting Ready,” shows some of the preliminary site work and underpinning of adjacent buildings that occurred prior to the actual start of foundation work.

These videos are purely educational and informative in nature: after all, in spite of the numerous problems that this building has, some of which I have discussed elsewhere on this blog (also here), it’s construction is actually quite interesting and in many ways unusual.

Given my prior and continuing criticism of the Milstein Hall design, I would like to acknowledge the support for this video project by the College of Architecture, Art & Planning (Dean Kent Kleinman) and the Construction Manager (Welliver McGuire). Of course, there is a contractual stipulation that some form of educational outreach must be provided along with the actual construction of the building — so my video project proposal, having little if any competition from other faculty initiatives, may have been viewed as a necessity to fulfill this contractual obligation. In any case, I appreciate the support I’ve been given. Disclaimer: Any views or opinions expressed on these videos are entirely my own (except where views or opinions are expressed directly by other people appearing in the videos), and are not necessarily the views of Cornell University, OMA, or any of the consultants, subcontractors, or construction managers involved in the construction of Paul Milstein Hall

Note: links to other Milstein posts updated May 5, 2011.

Cornell’s Fine Arts Library

[numerous updates below: 7/26/11 – 12/12/13; some nonfunctioning links re-directed Feb. 29, 2016]

It is often necessary to anticipate future developments and trends in order to make recommendations for the renovation of building space or the construction of new space. Paul Milstein Hall at Cornell University (Rem Koolhaas, OMA architects) is an example of new construction resulting from an analysis of spatial needs. It is also an example of what can only be called a squandering of resources since these needs could have been met with far less expenditure of such resources.

Part of what didn’t make sense in the planning of Milstein Hall was its connection at the second-floor level to the Fine Arts Library in Sibley Hall. For security reasons, this connection would have been difficult to implement, and it is likely that the doors between Milstein and Sibley Halls would have remained locked and unusable. Cornell would not permit such issues to be considered in the planning for Milstein Hall, so that the decision to link Milstein to the library space always seemed dubious.

2nd-floor plan, Milstein Hall, Cornell University

2nd-floor plan, Milstein Hall, Cornell University


On March 24, 2010, I was called to the Dean’s office to discuss his plan to move the Fine Arts Library out of Sibley Hall, replacing it with studio space and faculty offices that are now in Rand Hall. The ultimate aim is to house the Fine Arts Library in Rand Hall. This appeared sensible for at least two reasons. First, it resolves the embarrassment of having Milstein Hall unable to connect with Sibley Hall: with design studios in Sibley and Milstein at the second-floor level, there would no longer be a security issue forcing the interconnecting doors to be locked. Second, Rand Hall appears to be a much stronger building than Sibley, which has always had problems actually supporting book stacks (unless they are spread out in an inefficient manner). Rand, on the other hand, could house books quite efficiently. In other words, Sibley has a wooden floor structure appropriate for studios, classrooms, and offices; while Rand has a steel and reinforced concrete floor system appropriate for heavier loads like libraries. [10/1/11 update: Moving the Fine Arts Library into Rand Hall is problematic for another reason. See my more recent blog post here.]

But Cornell, in its wisdom, did not plan for such a move, and will not pay for it. Apparently, the only way to accomplish this is to use money already being spent by the college to rent space on Esty Street (downtown Ithaca). By implementing an elaborate phasing plan — in which Esty St. studios are moved to Rand Hall’s first floor, displacing faculty offices which are moved into the Fine Arts Library space, displacing books which are moved either into more dense stack areas under the dome, or into the library’s annex — it seems possible to take the Esty St. rent and apply it to the limited (and temporary) renovation of Sibley and Rand Hall as described above. Ultimately, fund-raising would need to occur so that the entire Fine Arts Library (or some portion thereof that is not housed in the annex) could be moved to a suitable home in Rand Hall, with faculty offices moved again (this time to the third floor of Sibley Hall), and studios moved from Rand Hall into Sibley’s second floor as well as into the soon-to-be-completed Milstein Hall.

But this plan raises another question about the future of libraries. When I talked to Dean Kleinman in March 2010, I suggested that the general strategy of reclaiming Sibley for studios and offices seemed to make much sense, especially since the Fine Arts Library could never logically connect directly to Milstein Hall from its current location in Sibley Hall. However, I made the point that, given the rapidly fading importance of physical books in academic life, it might be wise to reconsider whether fund-raising for a new library home in Rand Hall was an appropriate use of resources. Increasingly, books and journals are accessed electronically; this trend is clearly accelerating, especially with devices like Kindles and iPads becoming available in recent years. Many academic books and journals are already available online as “electronic resources” through Cornell’s library system.

A recent article in the Cornell Chronicle dated June 29, 2010 confirms that Cornell’s engineering library at Carpenter Hall is being dismantled effective next year, since it was discovered that “approximately 99 percent of the use of the collection consists of online materials.” [UPDATE 8/13/10: two additional libraries at Cornell are being “re-imagined”: see Chronicle article here.] In fact, what stands between a fully digitized world of knowledge and the ability to gain access to that knowledge is neither technology nor resources per se, but rather an unholy alliance of forces intent on preserving the infrastructure of what is called intellectual property so that the unfettered diffusion of knowledge can continue to be held hostage to the demands of copyright owners.

Here we see before us a classic instance of the relations of production (including the legal infrastructure defining intellectual property) falling far behind the actual means of production (including the digitization of what were previously physical books and journals). It can already be seen how these relations of production are changing in response to the developing reality of the Internet. See, for example, Google vs. Viacom.

Cornell’s College of Architecture, Art & Planning’s Fine Arts Library is one of the nation’s best. Implicit in Dean Kleinman’s plan to create a new mausoleum for the Fine Arts Library’s physical collection is an attempt to preserve this competitive advantage by renovating new space for the collection. But in an age when physical collections of books will have little utility, except as objects admired in book museums, this appears to be another questionable space-allocation decision and points to the past rather than the future. Instead, Cornell should be working to accelerate the digitization of its (and all other) collections, and to participate in movements aiming for the unfettered distribution of all scholarly works in open-access networks.

[July 26, 2011 update] A just-announced partnership between Cornell and Columbia University libraries is revealing in this regard. Anne Kenney, Cornell’s head librarian, characterizes this partnership as “choosing collaboration over competition” (See Chronicle Online 7/15/11 article) as if corporate mergers — increasing market share and operational efficiencies — are ever about “collaboration over competition.” In fact, an undated article on Cornell’s library web site [link no longer works, but article can be found here, dated Oct. 14, 2009] more accurately describes the motivations and results of such a collaboration: “to achieve greater efficiencies and effectiveness” (James G. Neal, VP for Information Services and University Librarian at Columbia) and “to improve the quality of collections and services offered to campus constituencies, redirect resources to emerging needs, and make each institution more competitive in securing government and foundation support.”

The point I made in the last paragraph of this post bears repeating. Treating academic information as property, intellectual or otherwise, is simply insane. It was insane when knowledge was largely embedded in physical objects (books and periodicals) and libraries competed to have the biggest and best collections; but when knowledge is now embedded largely in digital files, the degree of insanity is impossible to exaggerate. The potential exists now to simply share all knowledge. That the Cornell and Columbia libraries (and they are hardly unique in this regard) exploit this potential as a means for competing against all others — for excluding the rest of the world from these resources — is indeed sad.

[update: March 15, 2012] Thinking of knowledge as intellectual property, and therefore as a means of competition (through which one excludes others from that knowledge to gain an advantage), is apparently the lens through which many Cornell faculty view library resources. This came to light in an article in the Cornell Daily Sun today, which stated: “According to the UFLB report, in 2010 Cornell was ranked 43rd in expenditures proportional to faculty members, 15th to students and 35th to Ph.D. fields among the 116 research libraries as assessed by the ARL.”

The idea expressed by faculty members in that article is that “our collection budget needs to stay competitive“; if not, then “we will not have the best library and won’t be successful in bringing the best faculty and students to Cornell.” That this is undoubtedly true is not the point. Rather, what is striking is the apparent lack of interest in creating a free and open-access platform where such knowledge becomes available and universal. After all, much of this knowledge is actually created by members of academic institutions, created without the expectation of remuneration and constrained in its free and universal distribution, not by the wishes of its creators, but by the archaic system of credentialing and publication that has become one of the most counter-productive aspects of academia — except, of course, from the point of view of those few institutions that are able to use this cumbersome and insane system as a means of competition against their peers.

[update: Dec. 12, 2013] Another Cornell library is being reduced in size: “…Mann Library consolidated its stacks onto its second and third floors this summer. The library based its plans to move around stacks on a study that assessed factors like the reduced need for stacks space and the need for more functional office space…” See this Cornell Sun article from Sept 29, 2013 [pdf made from this low-res archival copy].

water in rand hall

While Milstein Hall construction has begun, Rand Hall (which will be connected to Milstein Hall, and which will contain mechanical equipment for Milstein Hall) is suffering from neglect. Storm water from two recent rains has backed up in the roof drain pipes and discharged through an eye wash fixture on the second floor, as can be seen in this short video. The water has worked its way down from the second floor into first floor offices (including my own). How is this possible? Somehow, someone has connected the waste pipes from a second-floor water fountain and eye wash fixture directly to the roof drain pipe, instead of connecting them to a sanitary sewer waste line with a proper vent.

milstein hall loses its barcelona chair

In a stunning, though entirely symbolic, concession to economic pragmatism or, more likely, to mitigate Milstein Hall’s apparent extravagance and elitist sensibility at a time when workers are being laid off and faculty salaries are frozen, Cornell has eliminated the symbolic centerpiece of Rem Koolhaas’s design for its new architecture building: Ludwig Mies van der Rohe’s iconic Barcelona chair has been rendered out of the official rendering of Milstein’s glass elevator, replaced with a plain vanilla chair.
Misltein before and after loss of Barcelona chair
On the other hand, why one even needs this glass elevator in a two-story building remains unclear: Milstein will be physically connected to two adjacent buildings, both with elevators, so that ADA-mandated access is already available. Can it be that architecture students require the constant stimulation provided by such mechanical contrivances in order to be properly initiated into the wacky world of high design?

elevators connected to Milstein Hall

Shock and awe: Cornell attacks the building code!

In 2007, I wrote to Peter Turner, Assistant Dean for Administration of the College of Architecture, Art, and Planning (AAP) at Cornell, urging him to take action on two issues affecting the major lecture room in Sibley Hall, room 157. First, the construction of OMA’s Milstein Hall (Rem Koolhaas, architect) would eliminate natural ventilation, making the room, which is already unbearable, illegal. Since Milstein is an addition to Sibley Hall, it would not be able to be built unless the ventilation issue in Sibley was resolved. I have discussed this in more detail elsewhere.

Second, the lecture hall has only one exit, which is nonconforming with modern building code standards. As it turns out, a recent code interpretation makes it illegal to occupy the lecture hall with only one exit and more than 50 occupants.

Rather than fixing the problem, and improving the safety of these rooms, Cornell has filed a lawsuit challenging the legality of the code interpretation. According to the Ithaca Journal [link no longer works — payment now required to access news archives] (6/17/09), Cornell spokesman Simeon Moss said that “We’re quite confident in the safety of the buildings.” Really? For everyone else building 50+ occupant lecture halls in the United States, two exits are always required, based on considerations of safety and risk. Cornell, however, is “confident” that its lecture halls are safe with only one means of egress. [Update: the Ithaca Journal (8/19/09) reports that Cornell has lost its lawsuit (link disabled by the Journal*); see my short video about the almost immediate creation of a second exit for the room.]

It should also be noted that Milstein Hall is being built with less fire separation between its new construction and the existing Sibley Hall than would be required under the current building code. Thus a fire in the Milstein addition would not only threaten Sibley based on this reduced level of fire separation, but any occupants of the lecture hall in room 157 would only have a single egress path, instead of two. Way to go, Cornell!

Cornell’s attitude is clearly not based on fire science, but on a misguided set of priorities that revolve around money: what is particularly egregious in this attitude is that they have simultaneously decided to spend more than $50 million on Milstein Hall, at a cost of over $1000 per square foot (compared to $400 per square foot or less for normal university facilities) while using up the $20 million Thomas endowment gift — which was intended to support ongoing program development for the architecture department — to pay off additional debt incurred by the high cost of construction.

* Updated 5/23/13: This article in the Cornell Daily Sun describes the lawsuit that Cornell lost. And here is the State of NY Supreme Court opinion.