Category Archives: Milstein-Rand-Sibley Hall

update on egress and mezzanine in Milstein Hall

Two issues have emerged with the construction of partitions in the crit space of Milstein Hall (Rem Koolhaas, OMA architects), under the concrete dome.

1. In a prior post, I mentioned that the interconnected spaces in Milstein Hall should probably not be permitted under the 2002 Building Code of NYS, since such an open geometry containing an unenclosed egress stair is legal only if no more than two stories are connected. Only if the “first-floor” lobby level is called a mezzanine — so that it becomes part of the lower-level space, reducing the number of stories from three (basement, first, and second) to two (first and second only) — do these interconnected spaces appear to comply with the Code.

However, the definition of a mezzanine has two requirements: it must have no more than one third the area of the room or space it is in; and it must be actually “in” the room or space it is in (the lower level crit space under the dome). I discussed the ambiguity of the requirement for the mezzanine to be “in” the crit space, but also warned that the whole pretense would fall apart if the crit space was subdivided in the future, since in that case, the lobby might no longer qualify as a mezzanine and the openings connecting three stories would clearly not be legal.

Figure 1. New permanent partitions being installed in the crit space of Milstein Hall

Figure 1. New permanent partitions being installed in the crit space of Milstein Hall

Well, the future is now. Partitions are being finished within the lower-level crit space (see Figure 1) that subdivide the larger space into smaller rooms or spaces. As can be seen in Figure 2, the largest of these newly-subdivided spaces is approximately 2,600 square feet, while the lobby is approximately 1,000 square feet. Since the lobby has an area that is more than one third that of the space below, it no longer qualifies as a mezzanine.

Figure 2. Comparison of lobby area and that of the room or space below

Figure 2. Comparison of lobby area and that of the room or space below

In other words, the lobby must be considered as a separate story, and the openings in what are now three interconnected stories become noncompliant, if they weren’t already.

2. The second issue has to do with required egress from spaces with more than 50 occupants. In a prior post I described the unacceptable location of exits in the crit space, since they are too close to each other to qualify as separate exits under the Code. Now that partitions are being constructed to subdivide the crit space, the same problem occurs in the smaller rooms being created.

Figure 3. Noncompliant exits in small crit space under the dome

Figure 3. Noncompliant exits in small crit space under the dome

The Code requires that any room with more than 50 occupants have two separate exits, and that these exits be a distance apart no smaller than one third the diagonal length of the room. To determine the number of occupants, one identifies the type of use, in this case an “assembly” occupancy with chairs that are not fixed. For such a use, the Code assigns 7 square feet per occupant. The area of the subdivided room in question, shown with a yellow tone in Figure 3, can be calculated as follows:

27 x 20 = 540 square feet
0.5 x 20 x 4 = 40 square feet
10 x 15 = 150 square feet
0.5 x 10 x 15 = 75 square feet

The total room area = 540 + 40 + 150 + 75 = 805 square feet.

Assuming 7 sq.ft. per occupant, the room must be designed for 805 / 7 = 115 occupants.

Even if the room had tables and chairs, like a classroom with 15 sq.ft. per occupant, it would still need to be be designed for 805 / 15 = 54 occupants.

Using either of these assumptions, two exits are required. The partitions only provide one exit. And this single exit is not wide enough to qualify as two exits based on its length compared to the diagonal length of the room.

The fact that these permanent partitions are movable shouldn’t change any of the conclusions drawn here. They are able to be configured in ways that are sometimes compliant and sometimes noncompliant, but they must be judged based on all possible geometries, especially those that put people and property in danger.

implausible egress interpretation

[Updated below] Aside from limiting the fuel within a given fire area through various compartmentation strategies, a fundamental component of all fire safety requirements is to provide protected paths of escape (egress) for building occupants in the event of a fire incident. The number and characteristics of these so-called means of egress depends on several variables, including the type of occupancy and the number of occupants. The large critique (crit) space under the dome of Milstein Hall (Rem Koolhaas, OMA architects) does not seem to meet these egress requirements.

The number of occupants in the crit space should be taken as the larger of (a) the actual number of anticipated occupants or (b) a number found by dividing the floor area of the space by the tabular floor area per occupant found in Table 1003.2.2.2 of the 2002 Building Code of NYS (Maximum floor area allowances per occupant). Following are the tabular values for assembly spaces — and the crit space certainly seems to count as an A-3 assembly space:

• Chairs only, but not fixed = 7 square feet per occupant
• Standing space = 5 square feet per occupant
• Unconcentrated, i.e., tables and chairs = 15 square feet per occupant

The most generous interpretation for the occupant use of this space would be “chairs, not fixed” with an allowance per occupant of 7 square feet. This corresponds to the reality of such critique assembly spaces, which can be crowded with students and faculty reviewers. Assuming an approximate floor area of 3,600 sq. ft. (the actual area may well be closer to 4,000 sq.ft.), the number of occupants in this space is 3600 / 7 = 514.

For any Group A or B space with 51 or more occupants, at least 2 exits from the space are required. Per Table 1005.2.1, three exits are required for 501-1000 occupants. Therefore, at least two, and possibly three, exits are needed from the crit space. It’s hard to imagine having more than 500 occupants in that space, as there are not that many architecture students in the entire program, but even with less than 500 occupants the requirement for two exits appears, at first glance, not to be met.

According to Section 1004.2.2.1 of the Code, and assuming that only two exits are needed, these two exits must be “placed a distance apart equal to not less than one half [or one third for this sprinklered space, per exception] of the length of the maximum overall diagonal dimension of the building or area to be served.”

Figure 1. Schematic plans showing how two noncompliant exits can be made compliant

Figure 1. Schematic plans showing how two noncompliant exits can be made compliant

As can be seen in Figure 1a, two exits from a room with more than 50 occupants cannot be placed next to each other, since the distance, d, must be at least one third the length of the diagonal distance, D. But what if we pretend that the room actually extends into the corridor, as shown by the shaded yellow area in Figure 1b? In that case, the two exits are now still not compliant, since even though one of them, E1, has been “moved” far enough away such that the distance, d, is now greater than one third of the distance, D. Nothing has changed to make the room safer, but and the exits are now still not compliant.

Of course, one needs One would need to stretch beyond plausibility the definition of a corridor to make this work. A corridor is a type of exit access, which the Code defines as follows: “That portion of a means of egress system that leads from any occupied point in a building or structure to an exit.” It seems clear that the corridor shown in Figure 1 really is acting as a corridor, and not as a part of the room. But the main point is this: even if the corridor is envisioned as “part” of the room, the egress situation remains noncompliant, because the occupants of the space still need to pass through what amounts to a single exit, rather than having two exits available. [see update 3 below] But how does this apply to the crit space in Milstein Hall?

Figure 2. Milstein Hall plans showing how two noncompliant exits can be made compliant

Figure 2. Milstein Hall plans showing how two noncompliant exits can be made compliant

If the second exit from the crit space is assumed to consist of the unenclosed stair leading to the bridge above the crit room space, this second exit (marked E2 in Figure 2) does not appear to conform to the requirement that it be a minimum distance from the first exit (marked E1) — this distance determined by dividing the maximum diagonal length of the room by three.

To solve this problem, the architects for Milstein Hall have attempted to use used the trick outlined above: as explained to me by Cornell’s Project Director for Milstein Hall, the crit space actually extends into what appears to be the corridor leading to the exit (see Figure 2b with the extent of the crit space shown in blue). In fact, there are even felt pin-up walls in this “corridor” to lend credence to this interpretation. Even so, the safety of the crit space appears to have been compromised by this imaginative Code interpretation.

[Update: Oct. 13, 2011] As I describe in a later post, the smaller crit spaces formed by new partitions also have egress problems.

[Update 2: Oct. 13, 2011] One might have more sympathy for the architects’ contention that the crit space actually extends into the corridor if they had indicated this intention on their plans. In fact, they label the corridor separately from the crit space (calling it a “gallery/ hall”) as can be seen in this annotated screen shot taken from Cornell’s Milstein Hall website:

room-labels

[Update 3: March 1, 2012] The deleted text and bold-face additions above are intended to clarify the point that I was trying to make: that the crit space under the dome in Milstein Hall (or any similarly configured space with more than 49 occupants) is noncompliant with egress regulations in building codes. This judgment was recently supported by a Code expert from the International Code Commission (which publishes the International Building Code upon which the New York State Building Code is based); I will publish his written opinion as soon as I receive it [the Code opinion can be found here].

milstein hall and its interconnected spaces

Milstein Hall at Cornell (Rem Koolhaas, OMA architects) contains what appears to be three floors, all interconnected with an opening through which passes an unenclosed egress stair. Such a condition, unless it is designed as an atrium with special smoke control measures, would not be permitted under the New York State Building Code — see my discussion of holes in floors.

Milstein Hall's interconnected spaces -- crit space below, lobby/bridge in the middle, and studios above -- can be seen in this image

Milstein Hall's interconnected spaces -- crit space below, lobby/bridge in the middle, and studios above -- can be seen in this image

I asked the Project Director for Milstein Hall how such an interconnected opening was possible, since the interconnected spaces were clearly not designed as an atrium. He explained that, contrary to appearances, the building only has two stories with no basement: what appears as the basement is actually the first floor; what appears as the first floor is actually a mezzanine; and only the second floor is really what it appears to be — the second floor. Mezzanines need to be no more than one-third the floor area of the room or space they are in, and the first-floor lobby of Milstein did appear to be no bigger than one-third the floor area of the crit space under the dome to which it is connected.

However, while the interconnected openings in Milstein Hall appear at first glance to meet the “letter” of the Building Code, they may well be noncompliant.
Figure 1
Comparing Case I and Case II in Figure 1, one can see that the entire rationale for allowing an unenclosed egress stair from the second floor to the mezzanine lobby depends on the relative area of the space defined by what I have schematically called wall “A.” If wall “A” is placed in such a way that the area of the space it forms is at least 3 times bigger than that of the lobby (Case I), then the lobby can be counted as a mezzanine, and the egress stair is then technically within an unenclosed opening connecting only two stories, thereby conforming with exception 8 or exception 9 in Section 1005.3.2 of the 2002 New York State Building Code.

However, if wall “A” is moved so that the area of the space it forms is less than 3 times the size of the lobby (case II), then the lobby cannot be called a mezzanine. It now becomes the first floor, and the same openings and egress stair become noncompliant.

This seems entirely irrational, since Case II, with less floor area to house combustible products and a smaller number of occupants than Case I, is nevertheless noncompliant, whereas Case I, with a larger area and therefore more occupants and potentially combustible products, would be deemed compliant.

It seems probable either that the writers of the Code never anticipated that their definition of mezzanine would be exploited in this way, or that other aspects of the mezzanine definition make this geometry noncompliant.

The definition of mezzanine, found in Section 502 of the 2002 Code, states that it must have “a floor area of not more than one-third of the area of the room or space in which the level or levels are located.” The key word here is “in.” The mezzanine must be “in” the room or space, not outside the room or space with an opening that connects them. Now, one might debate what exactly the meaning of the word “in” is (by analogy to Bill Clinton insisting that a proper interpretation of his prior testimony “depends on what the meaning of the word ‘is’ is”). As can be seen in Figure 2, common sense would suggest that the lobby is not “in” the dome. Both the section (Figure 2a) and the composite photo (Figure 2b) show clearly that the concrete structure of the dome creates a distinct “room” or “space” and that the lobby (pictured through the hole in the dome visible at the left of Figure 2b) is completely outside that space.

Figure 2

It is possible (along the lines advocated by Clinton) to define “in” topologically rather than by recourse to “common sense”; in that case the lobby can indeed be tested as a mezzanine “within” the dome “crit space.” In other words, we could draw a continuous contour line through the opening connecting the two spaces and call the resultant figure a single space. But the Code is fairly careful about the prepositions it deploys. If the intent were to allow a mezzanine to have any interconnected relationship to a room or space, other words or phrases could have been chosen instead of “in” or “within.” The Code does not describe a mezzanine as being “next to” or “adjacent to” or “connected to” some other room or space: it specifically says that a mezzanine must be “within” a room.

Still, this is admittedly ambiguous. The commentary to the 2009 IBC doesn’t really help: “So as not to contribute significantly to a building’s inherent fire hazard, a mezzanine is restricted to a maximum of one-third of the area of the room with which it shares a common atmosphere.” Here, the phrase “common atmosphere” has two purposes: first, it signals that the mezzanine must be somehow contiguous with the space it is in; second, it excludes any “enclosed portion of a room” in computing “the floor area of the room in which the mezzanine is located.” Having a “common atmosphere” appears therefore to be a necessary, but not sufficient condition. The mezzanine must also be “in” the room or space, which again brings us back to the question of what “in” is.

But this much is true: if the lobby space cannot be called a mezzanine, then it counts as a story. In that case, the interconnected openings are noncompliant, as they meet none of the exceptions for shaft enclosures outlined in Section 707.2 of the 2002 Code. And even if the lobby is now granted the status of mezzanine, the crit space under the dome becomes locked into its current geometry forever: it can never be reconfigured, for example, into a series of smaller rooms, since the lobby would then exceed its maximum floor area qua mezzanine and would revert back to being a separate story. The opening connecting what would now be three interconnected stories would be noncompliant.

[Update: Oct. 13, 2011] As I describe in a later post, the crit space has now been subdivided into a series of smaller rooms, appearing to make both the lobby noncompliant as a mezzanine, and the interconnected stories with an unenclosed egress stair noncompliant according to the various allowable exceptions for shaft enclosures.

problems with the third-floor exterior wall of East Sibley Hall

[updated below Oct. 13, 2011 and March 9, 2012] Appendix K of the 2002 New York State Building Code made significant changes to the model 2000 International Building Code (IBC) upon which the New York State Code was based. It allowed a building addition to “increase the area of an existing buiding beyond that permitted under the applicable provisions of Chapter 5 of the Building Code for new buildings” as long as a fire barrier was provided.

Normally, a fire wall — not a fire barrier — would be required in such cases, but NYS legislators wanted to make it easier and less expensive (and therefore less safe) to build additions to existing structures. Whereas it is absolutely clear what a fire wall is, and where it must be placed in relation to the parts of a building it is separating, this hastily contrived NYS appendix doesn’t bother to specify exactly where its alternative fire barrier must be provided.

This wouldn’t be much of a problem if the addition were the same height as the existing building. However, Milstein Hall at Cornell University (OMA – Rem Koolhaas architects) is a two-story building addition connected to Sibley Hall, which is a three-story building (see building section below, adapted from Cornell’s Milstein Hall web site). The architects for Milstein initially had called for a fire barrier between the two buildings, but only on the second-floor where they literally connect. It was only later, when this assumption was challenged, that they added fire barrier protection at all levels where the two buildings come into contact (i.e., at the basement and first-floor levels as well) — see update below. Left with no protection at all is the thrid-floor exterior wall of E. Sibley Hall overlooking Milstein’s green roof.

Section showing Sibley and Milstein Halls (adapted from Cornell's Milstein Hall web site)

Sibley and Milstein Halls (adapted from Cornell's Milstein Hall web site)

This is a problem for two reasons. First, the window openings on the third floor of Sibley have no fire protection. Second, the wooden load-bearing exterior wall of Sibley’s third floor has no fire-resistance rating. None of this was a problem when Sibley was a non-conforming, grandfathered, free-standing building. It becomes a problem with the construction of Milstein Hall.

The 2002 New York State Code (specifically, Section 704.10), under which Milstein was permitted, requires that “opening protectives” be provided “in every opening that is less than 15 feet (4572 mm) vertically above the roof of an adjoining building or adjacent structure that is within a horizontal fire separation distance of 15 feet (4572 mm) of the wall in which the opening is located.” All of the window openings in the third floor of E. Sibley Hall that overlook Milstein Hall qualify under this section for opening protectives. The only exception to this requirement is where the roof construction below the openings has a 1-hour fire-resistance rating and its structure (i.e., the steel beams and girders supporting the roof) has a 1-hour fire-resistance rating. Milstein’s roof structure has no fire-resistance rating, so the exception does not apply.

Not only do Sibley’s third-floor windows require opening protectives, but the entire exterior wall on the third floor of Sibley (facing Milstein Hall) needs to be reconstructed with a 1-hour fire-resistance rating. Footnote “f” in Table 601 (exterior bearing walls) requires that the fire-resistance rating of the wall be not less than that based on fire separation distance (Table 602). Table 602 requires a 1-hour fire-resistance rating for Occupancy Groups A or B if the fire separation distance is less than 5 feet.

The fire separation distance between Sibley and Milstein Halls is 0 feet (they are physically connected), based on the most generous assumption that one can make, i.e., that they are effectively two separate buildings. Actually, Appendix K only allows them to be considered as separate buildings from the standpoint of “area” (K902.2). However, if they were considered as a single building — as would be required under the current building code (i.e., without a fire wall) — then all of this discussion would be moot since Milstein Hall would be clearly noncompliant. Either way one looks at it — as a single building or as two separated buildings — the current situation appears to be noncompliant.

[Update: Oct. 13, 2011] As it turns out, the nonconforming fire barrier placed between Sibley and Milstein Hall — to satisfy the ambiguous requirements of Appendix K from the 2002 Building Code of NYS — is not only nonconforming but also noncompliant. The width of fire-rated openings in such a fire barrier cannot exceed 25 percent of the length of the fire barrier wall. In the image below, the aggregate width of openings is shown graphically in relation to the total length of the fire barrier wall. It can be seen that the opening width greatly exceeds the 25 percent limit:

sibley-2nd-floor-small

[Update: March 9, 2012] A noncompliant solution to the fire barrier problem was proposed and recently installed. At great expense. And completely useless. See my analysis here.

cornell’s fine arts library in Rand Hall

There are plans to move Cornell’s Fine Arts Library from Sibley Hall, where it has existed as a nonconforming (”grandfathered”) occupancy for quite a few years, to Rand Hall, which is now connected to Sibley Hall through newly-constructed Milstein Hall. Because the addition of Milstein Hall was, and is, nonconforming with respect to the current New York State Building Code, it may not be possible to put a library occupancy in Rand Hall. I made a similar argument about placing so-called Group A occupancies in Sibley Hall. This same explanation applies to Group A occupancies in Rand.

A future change to an A-3 (library or lecture hall) occupancy in Rand Hall should not be permitted, because such a change would be replacing an existing occupancy with one of a higher hazard. The relevant code language is as follows: Section 812.4.2.1 of the Existing Building Code of New York State says: “When a change of occupancy group is made to a higher hazard category as shown in Table 812.4.2, heights and areas of buildings and structures shall comply with the requirements of Chapter 5 of the Building Code of New York State for the new occupancy group.” Table 812.4.2 classifies group A-3 spaces as having a “relative hazard” of 2 (with 1 being the highest hazard), and group B spaces (the current occupation of Rand’s 2nd and 3rd floor, per email from City of Ithaca Senior Code Inspector John Shipe) as having a relative hazard of 4 (lowest hazard). Therefore, it is clear that a change from group B to group A-3 constitutes an alteration to a higher hazard occupancy.

With such a change, the building — which under the current building code is defined as Rand-Sibley-Milstein — must conform to the requirements of Chapter 5 of the current Building Code of New York State. What are those requirements? Chapter 5 regulates the allowable heights and areas of buildings, based on construction type and occupancy. Since the fire barrier separating Milstein and Sibley Halls is nonconforming with respect to the current code, it [i.e., the fire barrier — clarification added 10/2/11] cannot be invoked to consider Rand-Milstein Hall as a separate building, as would be the case with a fire wall. Therefore, Rand-Sibley-Milstein must be treated as a single building under the current code, and the height/area limits are as follows: the maximum height is 60 feet; the maximum number of stories is two; and the maximum area on a single floor is at most 22,500 sq.ft. The combined second-floor area for Rand-Sibley-Milstein greatly exceeds this limit of 22,500 sq.ft., and the number of stories in Rand-Sibley-Milstein similarly exceeds the Code limit of two. Based on either of these criteria (floor area or number of stories), any alteration to a higher hazard occupancy should not be permitted, as the requirements of Chapter 5 would not be met, and cannot be met.

In other words, putting the library on the 3rd floor of Rand would violate the Code limit of two stories; putting the library on the 2nd floor of Rand would violate the floor area limit.

[Update: Oct. 13, 2011] The move of the Fine Arts Library into Rand Hall has taken place this past week, in spite of the objections I have raised. Here are a few additional points, for the record:

1. On Oct. 7, 2011, I sent an email to the Milstein Hall project director which included this clarification:

“I didn’t mention this to GW at today’s meeting, but my notes that I gave him on Code issues (attached) state that: ‘the exception [to Section 912.5.1 of the Existing Building Code of NYS] only permits a fire barrier, if used in lieu of a fire wall, to meet area limitations for the new occupancy — NOT height limitations. Only a fire wall can meet both height and area limitations for the new occupancy.’ In other words, the library move to the 3rd floor of Rand will not be in compliance even if the fire barrier between Rand and Milstein is upgraded. Only a fire wall would make such a move compliant. On the other hand, an upgraded fire barrier would appear to allow such a move to the second floor of Rand Hall. In either case, the current fire barrier is noncompliant.”

2. The contention that a library (A-3 occupancy) constitutes a higher hazard occupancy compared to the current use in the Rand Hall space is the underlying reason why such a move is noncompliant. The Code is unambiguous about the occupancy of libraries as A-3. Design studios are not specifically mentioned in the Code; rather, they fall under the Group B definition for educational occupancies above the 12th grade. If there was any doubt about the legitimacy of this classification, the Ithaca Building Department files for Rand Hall contain numerous documents, all confirming that the Group B designation was actually used for the studio spaces in Rand Hall. Older documents in the file show a C5.5 designation; this was the old New York State Code subcategory for Educational occupancies within the “Commercial” category — exactly equivalent to the modern Group B designation. See this document copied from the Rand Hall Building Department file.

3. Even if a fire wall were built between Rand and Milstein Halls, it would still be necessary to upgrade the two egress stairs in Rand Hall, which are noncompliant once the occupancy on the third floor changes to a higher hazard. For details, see my email to the Milstein Hall project director.

milstein – uris comparison

Walking across Cornell’s campus the other day, I was struck by the similarity between Uris Hall, designed by Gordon Bunshaft (Skidmore, Owings & Merrill) in the 1970s, and Paul Milstein Hall, designed by Rem Koolhaas (Office for Metropolitan Architecture – OMA) in the 2000s.

Facade of Uris Hall (S.O.M.) applied to the rendering of Milstein Hall (O.M.A.).

Both buildings consist of  large, essentially square, floor plates supported by rigid frames (vierendeel trusses) lifted off the ground and cantilevered in dramatic fashion from their points of support. Both buildings also hover over large, below-grade, auditoriums: in the case of Uris Hall, the auditorium sits politely under the podium; in Milstein Hall, the auditorium rides a reinforced concrete dome that seems to burst through the ground plane. Both buildings mediate their cantilevered steel superstructures and highly-articulated bases with a glass wrapper designed to enclose space and provide an entry at grade without compromising the visual articulation of superstructure and base.

Official rendering of Milstein Hall.

Code compliance issues in E. Sibley Hall, Cornell

Following is a transcription of an email that I wrote to the Dean of the College of Art, Architecture, & Planning at Cornell University on Sept. 6, 2010 (copied to the Assistant Dean for Administration, AA&P; the Project Director for Milstein Hall; and the Building Commissioner and Deputy Building Commissioner of the City of Ithaca) [9/10/10 updates below]:

Portions of East Sibley and Rand Halls are in serious danger of being noncompliant with the NYS Building Code, and their ability to remain occupied for library, studio/classroom, and office use may be in jeopardy.

Once the floor/roof structure of Milstein Hall is in place, two things immediately occur that threaten the continued occupation of the adjacent, connected buildings.

First, all covered space under the structure of Milstein Hall counts as building area for Sibley Hall whether or not those spaces are enclosed, since a fire barrier is not yet in place to separate the two structures. Under these current circumstances, East Sibley Hall contains floors whose areas — that is, the combined, unseparated, floor areas of East Sibley and Milstein Halls — exceed that allowed by the Code, given the limits imposed by the governing V-B construction type for Sibley Hall.

Second, once the floor/roof structure of Milstein Hall is in place, the windows in Sibley Hall under these covered spaces no longer function as openable windows for the purpose of natural ventilation. I understand that Cornell and City of Ithaca Code Enforcement officials have challenged this contention, but I must insist that it remains true. As I pointed out previously, the Code limits natural ventilation to windows opening to “yards” or “courts.” Yards and courts must be “uncovered space, unobstructed to the sky” (see chapter 2 definitions in the Code). The Code does not permit windows used for natural ventilation to open into any other type of spatial geometry, whether or not “outdoor air” can somehow work its way to the window opening. The Commentary to the Code (written for the International Building Code, or IBC, from which the NYS Code derives) is absolutely unambiguous: “In order that adequate air movement will be provided through openings to naturally ventilated rooms, the openings must directly connect to yards or courts with the minimum dimensions specified in Section 1206” (Commentary for Section 1203.4.3 Openings on yards or courts). Since the openings “must directly connect to yards or courts” and since yards and courts must be “uncovered space, unobstructed to the sky,” the East Sibley windows at or below the second-floor of Milstein do not provide natural ventilation. Without mechanical ventilation that meets the criteria specified in the New York State Mechanical Code, the rooms are noncompliant and should not be occupied. In prior emails, I have outlined why the ad hoc provision of room air conditioner units or fans does not satisfy the requirements of the Mechanical Code. Yet aside from such rooms, it is clear that classrooms (e.g., 142-144 ES) or library spaces (e.g., the entire second-floor F.A.L. In E. Sibley) that have absolutely no mechanical ventilation will certainly not meet those Code requirements.

The second floor of Rand Hall, due to changes in the window configuration that have reduced the openable area, also has problems meeting Code criteria for natural ventilation. The current second-floor studio area (field measurements taken 9/3/10, excluding enclosed computer rooms, etc.) encompasses 5,259 square feet. The required vent area from openable windows is 4% of 5,259, or 210.4 square feet. However, the actual available vent area from openable windows, equal to 15 windows times 11.625 square feet of vent area per window, is only 174.4 square feet total. This is clearly noncompliant, and yet no mechanical ventilation is being planned for the studio space [see prior comments].

It is not my intention to speculate as to why East Sibley Hall and the second floor of Rand Hall are being occupied in spite of these apparent Code violations (lack of required ventilation in Rand and East Sibley Halls; and lack of fire barrier protection in East Sibley Hall). But whatever the reasons, the problems need to be addressed. It seems to me that either the noncompliant spaces should be vacated until Sibley/Milstein/Rand Hall is completed, or the twin problems of ventilation and fire protection should be corrected immediately.

Update 1 (9/10/10):

Two passages from NFPA 241: Standard for Safeguarding Construction, Alteration, and Demolition Operations (1996 version quoted here) support my argument about the immediate need for a fire barrier (the NFPA standard mentions “fire wall,” but the same logic applies to a “fire barrier” used as a substitute for a fire wall) between Sibley Hall and Milstein Hall:

1-1.1
Fires during construction, alteration, or demolition operations are an ever-present threat. The fire potential is inherently greater during these operations than in the completed structure due to previous occupancy hazard and the presence of large quantities of combustible materials and debris, together with such ignition sources as temporary heating devices, cutting/welding/plumber’s torch operations, open fires, and smoking. The threat of arson is also greater during construction and demolition operations due to the availability of combustible materials on-site and the open access.

6-6 Fire Cutoffs.
Fire walls and exit stairways, where required for the completed building, shall be given construction priority for installation… [and yes, the fire barrier is required for the completed building].

Update 2 (9/10/10):

I want to clarify that both of the actions I am recommending (mechanical ventilation for E. Sibley Hall rooms adjacent to Milstein Hall; and installation of a fire barrier in all E. Sibley Hall windows adjacent to Milstein Hall) are already part of the Milstein Hall scope of work. The issue is not whether they are required — they are both required and included in the Milstein Hall budget — but whether E. Sibley Hall can remain occupied during construction without these two items being put into place. In my view, the Code is clear on both issues: E. Sibley Hall should not remain occupied without adequate provision for ventilation and fire protection.

Furthermore, since both of these items are already part of the Milstein Hall scope of work, it is absolutely incomprehensible why the project’s phasing plan did not prioritize these two items so that E. Sibley Hall could remain safely occupied during construction. Well, actually, it is not so incomprehensible: the initial plans and specifications submitted to the City of Ithaca Building Department for a building permit included neither a proper fire barrier nor adequate mechanical ventilation for Sibley Hall. It was only after I raised objections through the FEIS comment process that the architects for Milstein Hall extended their fire barrier to the first and basement floors of Sibley Hall, and accepted the need for mechanical ventilation in Sibley Hall (after deciding to put fixed fire-rated glazing in all E. Sibley windows adjacent to Milstein). These architects still have not admitted that natural ventilation from windows under Milstein Hall is no longer a possibility given Code requirements for “yards” and “courts” adjacent to all windows used for natural ventilation; and continue to maintain that it is only because of the fixed glazing required for their fire barrier design that mechanical ventilation becomes necessary.

Construction of Milstein Hall

I’ve just posted the first of a series of informal “construction” videos showing how Paul Milstein Hall (OMA/Rem Koolhaas) at Cornell University is being built. The homepage for the anticipated video series is here. Ultimately, I hope to add additional short videos dealing in turn with substructure, superstructure, and enclosure systems.

The first video, “Getting Ready,” shows some of the preliminary site work and underpinning of adjacent buildings that occurred prior to the actual start of foundation work.

These videos are purely educational and informative in nature: after all, in spite of the numerous problems that this building has, some of which I have discussed elsewhere on this blog (also here), it’s construction is actually quite interesting and in many ways unusual.

Given my prior and continuing criticism of the Milstein Hall design, I would like to acknowledge the support for this video project by the College of Architecture, Art & Planning (Dean Kent Kleinman) and the Construction Manager (Welliver McGuire). Of course, there is a contractual stipulation that some form of educational outreach must be provided along with the actual construction of the building — so my video project proposal, having little if any competition from other faculty initiatives, may have been viewed as a necessity to fulfill this contractual obligation. In any case, I appreciate the support I’ve been given. Disclaimer: Any views or opinions expressed on these videos are entirely my own (except where views or opinions are expressed directly by other people appearing in the videos), and are not necessarily the views of Cornell University, OMA, or any of the consultants, subcontractors, or construction managers involved in the construction of Paul Milstein Hall

Note: links to other Milstein posts updated May 5, 2011.

Cornell’s Fine Arts Library

[numerous updates below: 7/26/11 – 12/12/13; some nonfunctioning links re-directed Feb. 29, 2016]

It is often necessary to anticipate future developments and trends in order to make recommendations for the renovation of building space or the construction of new space. Paul Milstein Hall at Cornell University (Rem Koolhaas, OMA architects) is an example of new construction resulting from an analysis of spatial needs. It is also an example of what can only be called a squandering of resources since these needs could have been met with far less expenditure of such resources.

Part of what didn’t make sense in the planning of Milstein Hall was its connection at the second-floor level to the Fine Arts Library in Sibley Hall. For security reasons, this connection would have been difficult to implement, and it is likely that the doors between Milstein and Sibley Halls would have remained locked and unusable. Cornell would not permit such issues to be considered in the planning for Milstein Hall, so that the decision to link Milstein to the library space always seemed dubious.

2nd-floor plan, Milstein Hall, Cornell University

2nd-floor plan, Milstein Hall, Cornell University


On March 24, 2010, I was called to the Dean’s office to discuss his plan to move the Fine Arts Library out of Sibley Hall, replacing it with studio space and faculty offices that are now in Rand Hall. The ultimate aim is to house the Fine Arts Library in Rand Hall. This appeared sensible for at least two reasons. First, it resolves the embarrassment of having Milstein Hall unable to connect with Sibley Hall: with design studios in Sibley and Milstein at the second-floor level, there would no longer be a security issue forcing the interconnecting doors to be locked. Second, Rand Hall appears to be a much stronger building than Sibley, which has always had problems actually supporting book stacks (unless they are spread out in an inefficient manner). Rand, on the other hand, could house books quite efficiently. In other words, Sibley has a wooden floor structure appropriate for studios, classrooms, and offices; while Rand has a steel and reinforced concrete floor system appropriate for heavier loads like libraries. [10/1/11 update: Moving the Fine Arts Library into Rand Hall is problematic for another reason. See my more recent blog post here.]

But Cornell, in its wisdom, did not plan for such a move, and will not pay for it. Apparently, the only way to accomplish this is to use money already being spent by the college to rent space on Esty Street (downtown Ithaca). By implementing an elaborate phasing plan — in which Esty St. studios are moved to Rand Hall’s first floor, displacing faculty offices which are moved into the Fine Arts Library space, displacing books which are moved either into more dense stack areas under the dome, or into the library’s annex — it seems possible to take the Esty St. rent and apply it to the limited (and temporary) renovation of Sibley and Rand Hall as described above. Ultimately, fund-raising would need to occur so that the entire Fine Arts Library (or some portion thereof that is not housed in the annex) could be moved to a suitable home in Rand Hall, with faculty offices moved again (this time to the third floor of Sibley Hall), and studios moved from Rand Hall into Sibley’s second floor as well as into the soon-to-be-completed Milstein Hall.

But this plan raises another question about the future of libraries. When I talked to Dean Kleinman in March 2010, I suggested that the general strategy of reclaiming Sibley for studios and offices seemed to make much sense, especially since the Fine Arts Library could never logically connect directly to Milstein Hall from its current location in Sibley Hall. However, I made the point that, given the rapidly fading importance of physical books in academic life, it might be wise to reconsider whether fund-raising for a new library home in Rand Hall was an appropriate use of resources. Increasingly, books and journals are accessed electronically; this trend is clearly accelerating, especially with devices like Kindles and iPads becoming available in recent years. Many academic books and journals are already available online as “electronic resources” through Cornell’s library system.

A recent article in the Cornell Chronicle dated June 29, 2010 confirms that Cornell’s engineering library at Carpenter Hall is being dismantled effective next year, since it was discovered that “approximately 99 percent of the use of the collection consists of online materials.” [UPDATE 8/13/10: two additional libraries at Cornell are being “re-imagined”: see Chronicle article here.] In fact, what stands between a fully digitized world of knowledge and the ability to gain access to that knowledge is neither technology nor resources per se, but rather an unholy alliance of forces intent on preserving the infrastructure of what is called intellectual property so that the unfettered diffusion of knowledge can continue to be held hostage to the demands of copyright owners.

Here we see before us a classic instance of the relations of production (including the legal infrastructure defining intellectual property) falling far behind the actual means of production (including the digitization of what were previously physical books and journals). It can already be seen how these relations of production are changing in response to the developing reality of the Internet. See, for example, Google vs. Viacom.

Cornell’s College of Architecture, Art & Planning’s Fine Arts Library is one of the nation’s best. Implicit in Dean Kleinman’s plan to create a new mausoleum for the Fine Arts Library’s physical collection is an attempt to preserve this competitive advantage by renovating new space for the collection. But in an age when physical collections of books will have little utility, except as objects admired in book museums, this appears to be another questionable space-allocation decision and points to the past rather than the future. Instead, Cornell should be working to accelerate the digitization of its (and all other) collections, and to participate in movements aiming for the unfettered distribution of all scholarly works in open-access networks.

[July 26, 2011 update] A just-announced partnership between Cornell and Columbia University libraries is revealing in this regard. Anne Kenney, Cornell’s head librarian, characterizes this partnership as “choosing collaboration over competition” (See Chronicle Online 7/15/11 article) as if corporate mergers — increasing market share and operational efficiencies — are ever about “collaboration over competition.” In fact, an undated article on Cornell’s library web site [link no longer works, but article can be found here, dated Oct. 14, 2009] more accurately describes the motivations and results of such a collaboration: “to achieve greater efficiencies and effectiveness” (James G. Neal, VP for Information Services and University Librarian at Columbia) and “to improve the quality of collections and services offered to campus constituencies, redirect resources to emerging needs, and make each institution more competitive in securing government and foundation support.”

The point I made in the last paragraph of this post bears repeating. Treating academic information as property, intellectual or otherwise, is simply insane. It was insane when knowledge was largely embedded in physical objects (books and periodicals) and libraries competed to have the biggest and best collections; but when knowledge is now embedded largely in digital files, the degree of insanity is impossible to exaggerate. The potential exists now to simply share all knowledge. That the Cornell and Columbia libraries (and they are hardly unique in this regard) exploit this potential as a means for competing against all others — for excluding the rest of the world from these resources — is indeed sad.

[update: March 15, 2012] Thinking of knowledge as intellectual property, and therefore as a means of competition (through which one excludes others from that knowledge to gain an advantage), is apparently the lens through which many Cornell faculty view library resources. This came to light in an article in the Cornell Daily Sun today, which stated: “According to the UFLB report, in 2010 Cornell was ranked 43rd in expenditures proportional to faculty members, 15th to students and 35th to Ph.D. fields among the 116 research libraries as assessed by the ARL.”

The idea expressed by faculty members in that article is that “our collection budget needs to stay competitive“; if not, then “we will not have the best library and won’t be successful in bringing the best faculty and students to Cornell.” That this is undoubtedly true is not the point. Rather, what is striking is the apparent lack of interest in creating a free and open-access platform where such knowledge becomes available and universal. After all, much of this knowledge is actually created by members of academic institutions, created without the expectation of remuneration and constrained in its free and universal distribution, not by the wishes of its creators, but by the archaic system of credentialing and publication that has become one of the most counter-productive aspects of academia — except, of course, from the point of view of those few institutions that are able to use this cumbersome and insane system as a means of competition against their peers.

[update: Dec. 12, 2013] Another Cornell library is being reduced in size: “…Mann Library consolidated its stacks onto its second and third floors this summer. The library based its plans to move around stacks on a study that assessed factors like the reduced need for stacks space and the need for more functional office space…” See this Cornell Sun article from Sept 29, 2013 [pdf made from this low-res archival copy].